Broadway & Littleton Blvd/Mineral Ave Intersection Reconstructions

  • Project typeTransportation (Intersection design & construction)
  • Project statusConcept Development
  • StartSpring 2025
  • Completion2027

Project Update

The project team has developed draft concepts for the two intersections. You can access them by clicking on the PDF link(s) below. The proposed changes are intended to improve operations and safety for all modes of travel using these intersections. These improvements stem from the Broadway Corridor Study. While current grant funding won't cover full intersection build-out yet, the concepts support key safety upgrades and position the city to complete the study’s recommendations in the future.

If you have questions or comments on the concepts, please provide them in the comment box shown below or send them to Shane Roberts, City of Littleton Transportation Planner, at sroberts@littletonco.gov. Please provide comments by May 13, 2026.

Overview

The City of Littleton received funding through the Colorado Department of Transportation (CDOT) Highway Safety Improvement Program (HSIP) to redesign the intersections of Broadway and Littleton Boulevard and Broadway and Mineral Avenue to increase safety for travelers of all modes, improve intersection operations, and improve multimodal facilities through each intersection.

Download the Project Information Sheet(PDF, 416KB)

Schedule Highlights

  • Fall 2025: Begin Concept Development
  • Spring 2026: Complete preliminary (30%) design
  • Winter 2026: Complete final design
  • 2027: Begin construction 