Do I need a ROW permit?
ROW permits are required for any work or equipment occupying the public ROW, including sidewalks and alleys. Refer to Littleton City Code Title 8-1-3.
Do I need a sewer permit?
The City no longer issues permits specifically for sewer-related construction. Instead, a ROW permit will be required to complete the work.
What materials are allowed for sewer service repairs?
Acceptable pipe includes Schedule 40 PVC or SDR 35. The pipe must have 6” of squeegee below the pipe and 12” of squeegee material above the pipe.
What backfill materials are allowed for street cuts?
Flash fill and flow fill are required to backfill streets cuts. Native material is not allowed to be used. Flash fill and flow fill must be onsite no later than 3:30pm or after-hours fees shall apply.
Are there requirements for street cuts?
Yes. All cuts must be straight edge cuts. Any cuts larger than 10’x10’ must be tested by a third-party during restoration. Third-party test results must be submitted to permits@littletongov.org within 48 hours. Additionally, steel plates are not permitted October through May.
How do I schedule an inspection online?
Use the link to Schedule an Inspection. You may refer to the eTRAKiT Help Guide for additional information.
How far in advance can I schedule an inspection?
Inspections can be scheduled up to seven days in advance.
Can I schedule a same-day inspection?
No. Inspection requests must be received by 11:59 pm on the business day prior to the requested inspection date.
I am doing emergency work. Will I be assessed a Non-compliance fee?
If the work is emergency work as determined by the City Engineer, a non-compliance fee will not be assessed.
What are examples of emergency work?
Repairs to broken water lines and blocked sewer service lines qualify as emergency work.
How do I schedule inspections for emergency work?
Inspections should be scheduled online through the eTRAKiT portal.
How much is the Non-compliance fee?
A first-offense fee of $250 will be assessed to the contractor for performing work without required permitting.
What are regular business hours?
Regular business hours for ROW and Sewer inspectors are Monday through Friday 8:00am to 5:00pm.
What is considered “after-hours”?
Saturdays, and weekdays before 8:00 am and after 5:00 pm.
How do I schedule an after-hours inspection?
After-hours inspections must be requested a minimum of 48 hours in advance by emailing permits@littletongov.org.
How much is the after-hours inspection fee?
The fee for after-hours inspections is $100 per hour, with a two hour minimum.
How and when do I pay the after-hours inspection fee?
After-hours inspection fees will be added to the permit and must be paid within the next business day.