Prince Street Link

  • Project typeTransportation
  • Project statusConstruction
  • CompletionSummer 2026

Project Overview

The Prince Street Link Project will provide safety and accessibility improvements along Prince Street between Lake Avenue to Alamo Avenue including reconstruction of the Prince Street and Church Avenue intersection. The enhancements will improve access and connections to several key area destinations including Downtown Littleton, Arapahoe Community College, Colorado School for the Blind, and the Regional Transportation District (RTD) Downtown Littleton Light Rail Station.

Project Improvements

The project will construct the following improvements along Prince Street between Alamo Avenue and Lake Avenue and as shown in the following graphic:

Reconstruction of the Prince Street and Church Avenue intersection will include:

  • Concrete roadway removal and replacement near the intersection
  • Sidewalk removals to construct wider for safer and more accessible sidewalks
  • Installation of Americans with Disabilities Act (ADA)-compliant curb ramps to allow people with mobility and sensory limitations to safely navigate crossings
  • Installation of bicycle lanes to increase bicycle safety and visibility
  • Upgraded traffic signal equipment to provide increased intersection safety through implementation of leading pedestrian intervals, and transit signal priority (for future use)

Improvements along Prince Street will include:

  • Removal and replacement of sidewalk along segments of Prince Street to provide safer and more accessible pedestrian facility. Where the width allowed, the sidewalk will be widened.
  • Installation of bike lanes in both directions Prince Street to increase bicycle safety and visibility
  • Removal of the asphalt roadway and replacement with concrete pavement for a more durable and lasting wearing surface (north of the Prince Street Bridge)
  • Removal and replacement of curb and gutter along segments of Prince Street
  • Installation of ADA-compliant curb ramps at the RTD bus stop driveways, at the West Lake Avenue intersection, and at the Church and Prince intersection

View the Prince Street Link Improvements Map(PDF, 454KB)

Project Funding

The project is funded by a Colorado Department of Transportation Safer Main Streets grant and local funds.

Schedule Highlights

  • 2017: Concept development
  • 2026: Final design completed
  • Summer 2026: Construction

Contact details

Project Manager
303-795-3863

Location

S Prince St & W Church Ave, Littleton   View Map