Main / Alamo / Prince - Bridge Fence Repairs

  • Project typeBridges
  • Project statusConstruction
  • StartFall 2025
  • CompletionSpring 2026
A map shows bridge repair sites along Main, Alamo, and Prince Streets in downtown Littleton.

Overview

The Alamo Avenue, Main Street, and Prince Street bridges are the three bridges providing access into and out of downtown Littleton. These three bridges are in the northern area of Littleton and cross over the Burlington Northern Santa Fe Railway (BNSF) and the Regional Transportation District (RTD) light rail lines. The fences and their associated infrastructure along these bridges have continued to deteriorate over time due to weather and infrastructure age.

The city has selected a contractor to complete several fence and infrastructure repair and maintenance activities along these three bridges to address these deteriorating conditions. Work includes:

  • Removing deteriorated steel fencing attached to the top of the existing concrete barriers on both sides of the bridges and replace it with new fencing.
  • New conduit with receptacles for electric service will be added to the top of the fences on the Alamo Avenue and Main Street bridges, and will be utilized primarily to power the decorations placed during the holiday months.
  • Removing and replacing existing monuments along each bridge.
  • Repairing any damaged or deteriorated existing concrete barriers.
  • Installing decorative metalwork to the fencing on Main Street and Alamo Avenue
  • Completing maintenance activities on the retaining walls along Alamo Avenue, Main Street, and Prince Street. These activities include removing debris, painting over graffiti, replacing damaged grates, and other maintenance work.

This repair and maintenance work will require full time sidewalk and lane closures in order to expedite the work, however through traffic will be permitted at all times and pedestrian detours will be clearly noted. Please visit the Cone Zone web page for traffic impacts and detours. The bridge repairs, maintenance and aesthetic improvements are funded through 3A funds.

Schedule highlights

The contractor will begin the bridge fence repair and maintenance work mid-October 2025 with anticipated completion in early March.

Contact details

Public Works Engineering
303-795-6863

Location

Alamo Avenue, Main Street, and Prince Street bridges over the BNSF and RTD rail lines., Littleton   View Map

Google Map