Euclid Neighborhood 2026 Street Reconstruction

  • Project typeTransportation
  • Project statusConstruction
  • StartSummer 2026
🚧 For traffic impacts and detours during construction, visit the Cone Zone page.

The Euclid Neighborhood 2026 Street Reconstruction project will reconstruct several streets (Euclid Avenue, Cedar Street, Datura Street, Elmwood Street, Arapahoe Road, and Carlson Drive) in the Stern Park and Ketring Park neighborhoods in Littleton. The project includes removal and replacement of roadway asphalt to create stronger and smoother driving surfaces. Curb and gutter will also be removed and upgraded along several areas to improve surface water flow and containment. The project will also include installation of new sidewalk as well as ADA-compliant curb ramps at several intersections to create safer and more accessible routes for pedestrians. The project is funded through the 3A Sales Tax Capital Improvement Fund. Construction is anticipated to begin in summer 2026 following the selection of a construction contractor.

The key project improvements along each street include the following.

View the Euclid Neighborhood 2026 Street Reconstruction project improvements map(PDF, 611KB)

Euclid Avenue (Windermere Street to Gallup Street)

  • Roadway asphalt will be removed and replaced from Windermere Street to Gallup Street
  • Roadway gutter will be removed and replaced in various sections along Euclid Avenue
  • Installation of new ADA-compliant curb ramps at several street intersection corners
  • Sidewalk will be removed and replaced along the north side of Euclid Avenue between Windermere Street and Gallup Street

Cedar Street (Ridge Road to Euclid Avenue)

  • Roadway asphalt will be removed and replaced from Gallup Street to the east end of Carlson Drive
  • Roadway gutter will be removed and replaced in various sections along Cedar Street

Datura Street (Ridge Road/Arapahoe Road to Euclid Avenue)

  • Roadway asphalt will be removed and replaced from Ridge Road/Arapahoe Road to Euclid Avenue
  • Sidewalk will be upgraded and extended on the west side of Datura Street from Euclide Avenue to Ridge Road
  • Roadway gutter will be removed and replaced in various sections along Datura Street

Elmwood Street (Arapahoe Road to Peakview Avenue)

  • Roadway asphalt will be removed and replaced from Arapahoe Road to Peakview Avenue
  • Curb, gutter and sidewalk will be replaced and upgraded at the intersection of Elmwood Street and Arapahoe Road, including installation of ADA-compliant curb ramps
  • Installation of new sidewalk and ADA-compliant curb ramps at the intersection of Elmwood Street and Euclid Avenue

Arapahoe Road (Ridge Road/Datura Street to Gallup Street)

  • Roadway asphalt will be removed and replaced from Ridge Road/Datura Street to Gallup Street
  • Installation of new sidewalk and ADA-compliant curb ramps at the intersections of Arapahoe Road and Gallup Street and Arapahoe Road and Elmwood Street
  • Installation of new sidewalk along the north side of Arapahoe Road from Ridge Road/Datura Street to Gallup Street

Carlson Drive (Gallup Street to Peakview Avenue)

  • Roadway asphalt will be removed and replaced from Gallup Street to the east end of Carlson Drive
  • New gutter will be installed along the western half of the south side of Carlson Drive.
  • Curb, gutter and sidewalks at the northeast and southeast corners of Carlson Drive and Gallup Street will be replaced and upgraded, including installation of ADA-compliant curb ramps

Contact details